Port LaBelle Utilities System

Water Use Permit and Well Services

Scope of Work

August 21, 2006 

 

Port LaBelle Utilities System (PLUS) seeks a SFWMD consumptive water use permit (CUP) for 1.2 mgd from the Sandstone Aquifer to supply a water treatment plant (WTP) currently under constructions and scheduled for completion in April 2007.  PLUS is currently supplied by two Sandstone Aquifer wells located on the site of the WTP, approximately 200 feet apart. PLUS seeks consulting services to assist in securing the water use permit by April 2007.  Four separate tasks are envisioned: an Aquifer Performance Test (APT), development of a drawdown impact model, preparation and submittal of a modification to CUP #26-00096-W, and design and construction of a new proposed production well at or near the WTP. 

Task 1: APT 

PLUS will provide access to both wells (PW1 and PW2) so that either a pressure transducer or a water level indicator can get into the production casing to measure water levels. It is proposed to pump PW2 and monitor PW1 and any other wells that can be found in the area. 

An In-situ data logger will be installed in both production wells (if possible) and any other wells that can be used. It is proposed to pump well PW2 at a constant rate of at least 500 gpm (0.72 mgd) for three full days or until a steady state is achieved. The data loggers will be installed and background water level data will be collected from all wells for at least 3 days prior to test start. For the drawdown and recovery tests, the data logger will be programmed to take water level readings every 0.005 minute logarithmically until 10 minutes is reached, and then readings will be recorded every 10 minutes until test termination. 

Field water quality data will be taken from well PW2 at the beginning of the test, after 24 hours and just before the termination of the test. The water will be tested for chlorides, temperature, specific conductance, and pH. 

Water will be discharged into the storage tank and/or an adjacent lake or the WTP surface water drainage system. 

After termination of the pump test, recovery water level data will be collected for 4 hours. 

The data will be analyzed using a programming system acceptable to SFWMD permitting staff.  A report will be written that will include the following: 

(a)     Geologic and hydrogeologic conditions at the site,

(b)     Description of all wells used as observation wells,

(c)     Description of the procedures used to run the constant rate discharge test,

(d)     Description of the data analysis, and appropriate figures. 

Task 2: Impact Model 

Using the aquifer parameter data from the APT (or previously determine aquifer parameter data), an analytical model will be used to run 90-day no recharge impact models. 

This model can reflect current existing users of the Sandstone Aquifer and any other aquifers potentially impacted by the PLUS extractions.  The modeling task will be used to help determine: 

(a)     Effects of proposed withdrawals on the Sandstone Aquifer.

(b)     The best location for the third production well (PW3).

(c)     Effects on other regional users of the Sandstone Aquifer

(d)     Effects on other local aquifers, if applicable. 

Based on District rules, an individual model with the proposed withdrawals by PLUS will first be modeled.  A second model must be run to include all legal existing users of the Sandstone Aquifer within the projected one-foot drawdown contour line of the individual model run.  An impact analysis report will be written to include a discussion of the model used and the results. 

Task 3: SFWMD Permitting 

For this task, the above information will be used as support for a request for the 1.2 mgd CUP and to add a third production well for PLUS. The initial services for this task should include: 

(a)     Attend one meeting with owner, project manager, and/or project engineer to discuss project objectives, if needed.

(b)     Acquire project CAD drawings from the project engineer that shows the project.

(c)     PLUS will provide the necessary population projection to substantiate the proposed increase.

(d)     Prepare all necessary graphics.

(e)     Complete and submit an application and supplemental forms for a SFWMD water use permit, CUP.

(f)       Respond to one letter from SFWMD Staff requesting additional information.

(g)     Coordinate the project with PLUS and SFWMD. 

Task 4: Well Design and Construction 

A third well (PW3) will be designed and constructed using all the available data. The task will include the following services: 

(a)     Assist PLUS in the preparation and submission of any required permits and applications to DEP

(b)     Prepare well specifications and contract well driller.

(c)     Oversee construction of the well and pump system.

(d)     Assist and verify that the construction process meets all terms of applicable permits.

(e)     Coordinate with well driller, pump installer, and PLUS.

(f)       Prepare report on well construction and pump installation. 

Budget 

Each task will be invoiced on a lump sum basis. Tasks 1, 2, and 4 will be invoiced upon completion of the task, with Task 3 being invoice upon submittal of the water use application.  The cost of each task are as outlined below: 

 

Task 1: Aquifer Performance Test            ______________________

 

Task 2: Impact Model                             ______________________

 

Task 3: SFWMD Permitting                    ____________________ 

 

Task 4: Well Design and Construction     ______________________