Port
LaBelle Utility System
Banyan
Village Water Supply Construction Project Update
John Capece
September 18, 2006
Based on meetings with Hendry
County staff, USDA Rural Utility Service grants administrators, and PLUS
Advisory Board members, the attached report & recommendation was submitted
to the Hendry County BOCC for consideration at the September 12 meeting.
The BOCC enacted the recommendations to (1) withdraw the USDA grant
application, (2) proceed with securing independent financing and (3) award a
construction contract to Forsberg Construction, Inc. for the two Banyan projects
(transmission line and distribution network).
The rationale for withdrawal of the
USDA application was to avoid additional project delays that would result from
waiting for the new USDA budget allocation and their subsequent eligibility
decision process for the Banyan projects. Moreover, the relatively good bid prices received from
potential contractors would soon expire and rebidding would likely increase
project costs significantly. The
bids were low due to unusual circumstances in a major Cape Coral utility project
that was temporarily suspended, idling the low-bid contractor. Regardless of bid expiration date, USDA would, for reasons of
procedure, require rebidding of the projects after the final USDA decision on
the grant/loan award package. Furthermore,
there was no certainty that USDA would, in fact, choose to fund the project
despite their verbal assurances that funds would likely be forthcoming.
Depending on the magnitude of any subsequent USDA grant, the federal
assistance could have been partially or entirely negated by the increase in
construction bids.
An additional consideration in the
decision to move forward without delay was that property assessments for Banyan
Village dramatically increased this year, creating a tax liability comparable to
lots in areas already served by water. Owners
in Banyan are paying dramatically higher taxes on lots that are not buildable
until the water services are provided.
Forsberg Construction, Inc.
contract for the transmission line is $2,265,,250 and their contract for the
distribution system is $5,763,468. CAS
originally presented two options for the design: (1) a 12” main transmission
line or (2) an 8” main line with a 500,000 gallon storage tank at an
additional cost of $800,000. The
Advisory Board and BOCC elected to go with the no-tank option, but increasing
the pipe size from 12” to 16”.
Using an assumption of 3600 taxable
lots in Banyan, the distribution system special assessment of $1640 per lot will
yield $5.9 million, very near the $5.8 construction plus other distribution
system costs. In the connection
charge is also a fee of $400 per lot for transmission main lines.
This will yield $1.4 million or $860,000 short of the construction costs
alone. Deducting the BOCC
contribution of $425,000 leaves a net shortfall of $435,000.
Distributed over the 3600 Banyan lots, this would increase the
transmission line connection charge from $400 to $521.
The current connection fees are
|
Charge |
Amount |
|
Water Plant Capacity |
$640 |
|
Water Plant Transmission Line |
$400 |
|
Water Main Area Distribution Line |
$540 |
|
Tap In |
$110 |
|
Water Meter Connection |
$170 |
TOTAL
|
$1850 |
The tentative connection fees for
Banyan (pending completion of the rate study) would be:
|
Charge |
Amount |
|
Water Plant Capacity |
$640 |
|
Water Plant Transmission Line |
$520 |
|
Water Main Area Distribution Line |
$1640 |
|
Tap In |
$110 |
|
Water Meter Connection |
$170 |
TOTAL
|
$3070 |